Note that due to the fixed-price nature of the original supply contract, the total cost of the plant was "only" €5.7B ($6.4B) to the owner/operator (TVO).
The $10B-$11B is the estimated cost to the plant supplier (Areva NP/Framatome), i.e. they made a huge loss.
Note that due to the fixed-price nature of the original supply contract, the total cost of the plant was "only" €5.7B ($6.4B) to the owner/operator (TVO).
The $10B-$11B is the estimated cost to the plant supplier (Areva NP/Framatome), i.e. they made a huge loss.
Finnish source of numbers: https://www.kauppalehti.fi/uutiset/olkiluoto-3-alkaa-tuottaa... (paywall)